Checking the lubrication system
HINT
- In case of downtimes of 1 to 4 weeks before commissioning, as a minimum check the lubricating film on guideways and racks (II) and the hydraulic lines for air bubbles and kinks (VII). If necessary, carry out a check of the complete lubrication system.
- As operator, check the lubrication system during initial commissioning, after downtimes of more than 4 weeks, if there is no lubricating film and after the cartridge or pump of the lubrication system has been replaced.
The operator is always responsible for adequate and properly functioning lubrication.
Cleaning agents |
---|
mild universal cleaner free from aromatic compounds (e.g. Motorex OPAL 5000) |
Lubrication ex works | Specification | Lubrication quantity |
---|---|---|
Elkalub FLC 8 H1 | Cannot be determined | Running surfaces of the roller and pinion need to be covered completely by a lubricating film |